Page 1 - Installation and Start-Up

Installation and Start-UpInfraStruXure®For Medium Data Centers40 kW 208/480/600 V

Page 3 - Contents

InfraStruXure System - Installation and Start-Up 7Installation ProceduresInstallation Procedure OverviewThis section provides the basic steps to insta

Page 4

Installation Procedures: Installation Procedure Overview8 InfraStruXure System - Installation and Start-Up6. Connect utility conductors to the PDU.For

Page 5 - - SAVE THESE INSTRUCTIONS

Installation Procedures: Installation Procedure OverviewInfraStruXure System - Installation and Start-Up 916. Configure the InfraStruXure Manager. For

Page 6 - Warnings

10 InfraStruXure System - Installation and Start-UpLevel the PDU, UPS, NetShelter, and XR Battery EnclosuresLeveling feet are attached under the enclo

Page 7 - Total Power Off

InfraStruXure System - Installation and Start-Up 11Exchange Side PanelsBefore installing the InfraStruXure PDU, Symmetra PX UPS, and XR Battery Enclos

Page 8 - Emergency Power Off (EPO)

Installation Procedures: Exchange Side Panels12 InfraStruXure System - Installation and Start-Up3. Remove the side panels from the sides of the PDU an

Page 9 - Site Planning

InfraStruXure System - Installation and Start-Up 13Join the PDU, UPS, and XR Battery Enclosures1. Move the PDU, Symmetra PX UPS, and XR Battery Enclos

Page 10

14 InfraStruXure System - Installation and Start-UpConnect Utility Conductors to the PDUElectrical Hazard: A licensed electrician must connect input c

Page 11 - Installation Procedures

Installation Procedures: Connect Utility Conductors to the PDUInfraStruXure System - Installation and Start-Up 15For overhead wiring: Remove the user

Page 12

InfraStruXure System - Installation and Start-UpAbout this ManualThis manual covers basic installation and start-up procedures for certified electrici

Page 13 - Tools Required

Installation Procedures: Connect Utility Conductors to the PDU16 InfraStruXure System - Installation and Start-UpRoute the input conductors to the Mai

Page 14 - Battery Enclosures

Installation Procedures: Connect Utility Conductors to the PDUInfraStruXure System - Installation and Start-Up 17At the Main Input switch, connect the

Page 15 - Exchange Side Panels

18 InfraStruXure System - Installation and Start-UpConnect AC Power and Control WiringElectrical Hazard: Only Field Service Engineers or qualified per

Page 16 - Symmetra PX UPS

Installation Procedures: Connect AC Power and Control WiringInfraStruXure System - Installation and Start-Up 19Connect control wiring. 1. Connect the

Page 17

20 InfraStruXure System - Installation and Start-UpConnect DC Power Wiring, if ApplicableElectrical Hazard: Only Field Service Engineers or qualified

Page 18

Installation Procedures: Connect DC Power Wiring, if ApplicableInfraStruXure System - Installation and Start-Up 21Connect power cables from the XR Bat

Page 19 - Install a circuit breaker

22 InfraStruXure System - Installation and Start-UpConnect an Emergency Power Off SwitchOverviewTo provide a mechanism for emergency power off, attach

Page 20 - Connect input conductors

Installation Procedures: Connect an Emergency Power Off SwitchInfraStruXure System - Installation and Start-Up 23Connect an EPO switch to the user con

Page 21

24 InfraStruXure System - Installation and Start-UpConnect User Input Contacts and Relay Outputs to the User Connection Plate Overview Make contact cl

Page 22 - Connect AC power wiring

InfraStruXure System - Installation and Start-Up 25Route and Attach Power Cables to the RacksOverhead WiringRoute and attach power cables to equipment

Page 23 - Connect control wiring

ContentsInfraStruXure System - Installation and Start-Up iSafety...1IMPOR

Page 24 - Cascade XR Battery Enclosures

Installation Procedures: Route and Attach Power Cables to the Racks26 InfraStruXure System - Installation and Start-Up– For single-feed devices within

Page 25 - XR (GND)

Installation Procedures: Route and Attach Power Cables to the RacksInfraStruXure System - Installation and Start-Up 27application) from the enclosure

Page 26 - Overview

28 InfraStruXure System - Installation and Start-UpRoute Data Cables to the InfraStruXure Manager Hub (or Switch)1. Connect a CAT-5 network cable (pro

Page 27

InfraStruXure System - Installation and Start-Up 29Start-Up ProcedureApply power to the systemSafety warningsThis section provides instructions on how

Page 28

30 InfraStruXure System - Installation and Start-Up6. Install at least one battery module (four battery units) in the Symmetra PX UPS. Install battery

Page 29 - Overhead Wiring

Start-Up Procedure: Apply power to the systemInfraStruXure System - Installation and Start-Up 318. Secure the power module:a. Tighten the screws on ea

Page 30 - Under Floor Wiring

Start-Up Procedure: Apply power to the system32 InfraStruXure System - Installation and Start-UpVerify UPS battery operation1. Read the messages displ

Page 31

Start-Up Procedure: Apply power to the systemInfraStruXure System - Installation and Start-Up 333. Command the UPS to turn off power to the load: a. P

Page 32 - Manager Hub (or Switch)

Start-Up Procedure: Apply power to the system34 InfraStruXure System - Installation and Start-UpVerify proper voltage and phase rotation at the UPS1.

Page 33 - Start-Up Procedure

Start-Up Procedure: Apply power to the systemInfraStruXure System - Installation and Start-Up 355. Close (turn ON) the Q2 circuit breaker on the PDU.3

Page 34

ii InfraStruXure System - Installation and Start-UpConnect DC Power Wiring, if Applicable . . . . . . . . . . . . . . . . . . . . . 20Cascade XR Batte

Page 35

Start-Up Procedure: Apply power to the system36 InfraStruXure System - Installation and Start-UpVerify bypass operationNote: The H3 LED above the Q3 c

Page 36 - Verify UPS battery operation

Start-Up Procedure: Apply power to the systemInfraStruXure System - Installation and Start-Up 373. Close (turn ON) the Q3 circuit breaker on the Infra

Page 37 - Confirmation Screen

Start-Up Procedure: Apply power to the system38 InfraStruXure System - Installation and Start-Up6. Close (turn ON) the Q2 circuit breaker on the Infra

Page 38 - Start the UPS

Start-Up Procedure: Apply power to the systemInfraStruXure System - Installation and Start-Up 392. Close (turn ON) the PDU distribution panel breakers

Page 40 - Verify bypass operation

InfraStruXure System - Installation and Start-Up 41Specifications40 kW InfraStruXure PDUElectrical PD40F6FK1-M PD40G6FK1-M PD40L6FK1-MInput Nominal Vo

Page 41

Specifications: 40 kW InfraStruXure PDU42 InfraStruXure System - Installation and Start-UpPower Cable Lengths variousRecommended Wire Sizing‡L1, L2, L

Page 42

Specifications: 40 kW InfraStruXure PDUInfraStruXure System - Installation and Start-Up 43.Configuration Delta to WYEMaximum Power Rating 60kVAMaximum

Page 43

03/2008990-1483C*990-1483C*APC Worldwide Customer SupportCustomer support for this or any other APC product is available at no charge in any of the fo

Page 44

InfraStruXure System - Installation and Start-Up 1SafetyIMPORTANT SAFETY INSTRUCTIONS - SAVE THESE INSTRUCTIONSThis manual contains important instruct

Page 45 - Specifications

2 InfraStruXure System - Installation and Start-UpWarningsInstallation/MaintenanceOnly a certified electrician can perform these tasks: • Connect the

Page 46 - L1, L2, L3, N

Safety: WarningsInfraStruXure System - Installation and Start-Up 3Total Power OffSet the UPS DC Disconnect circuit breaker and System Enable switch t

Page 47

Safety: Warnings4 InfraStruXure System - Installation and Start-UpDANGER—Risk of Electric Shock!Electrical Hazard: Hazardous, live parts inside the Sy

Page 48 - *990-1483C*

InfraStruXure System - Installation and Start-Up 5Site PlanningSpace ConsiderationsUse the figure below to determine the space requirements for instal