Battery Module Storage and Replacement (Symmetra PX and Smart-UPS VT) - 990-2958B 1
Battery Module Storage and Replacement
(Symmetra
®
PX and Smart-UPS
®
VT)
Directions for replacement
Battery Enclosures with four batteries in a row.
APC recommends that a whole battery module (one row of batteries) is replaced at the same time to
ensure optimal run-time (see Example 1). However it is only necessary to replace two batteries at the
same time according to Example 2 and 3 in the table below.
Battery Enclosures with two modules in a row.
Replace both batteries in one row at the same time.
Warning: Only trained persons familiar with the construction and operation of the
equipment, as well as the electrical and mechanical hazards involved, may install
and remove system components.
Caution: Wait until the system is ready to be powered up before installing Battery
Modules in the UPS. Failure to do so can result in a deep discharge of the batteries and
cause permanent damage (the time from the battery installation time till the UPS is
powered up should not exceed 72 hours or 3 days).
Caution: Do not mix battery units. Replace with same model.
Column A Column B Column C Column D
Example 1
New New New New
Example 2
New New Old Old
Example 3
Old Old New New