InRow RC Installation20
Filling and Purging
When the equipment is properly piped, begin the filling process (top piping configuration shown).
1. Open the 2-way supply valve and the 2-way bypass shutoff valve.
2. Using a 2.5-mm hex key, turn the flow control actuator to the fully open position.
DANGER
HAZARD OF ELECTRIC SHOCK, EXPLOSION, OR ARC FLASH
Turn off all power supplying this equipment before working on the equipment.
Failure to follow these instructions will result in death or serious injury.
na1767a
Flow control
actuator
Fully open
Full bypass
Full open
Fully open
2-way supply
valve
2-way bypass
shutoff valve
Fully closed
Fully closed