A. General: Preparation and installation shall be in accordance with reviewed product data, final shop
drawings, manufacturer’s written recommendations, and as indicated on the Drawings.
B. Factory-Assisted Start-Up: If a factory-assisted UPS start-up is requested, factory-trained service
personnel shall perform the following inspections, test procedures, and on-site training:
1. Visual Inspection:
a. Inspect equipment for signs of damage.
b. Verify installation per manufacturer's instructions.
c. Inspect cabinets for foreign objects.
d. Inspect battery units.
e. Inspect power modules.
2. Mechanical Inspection:
a. Check UPS and external MBC internal power wiring connections.
b. Check UPS and external MBC terminal screws, nuts, and/or spade lugs for tightness.
3. Electrical Inspection:
a. Verify correct input and bypass voltage.
b. Verify correct phase rotation of mains connections.
c. Verify correct UPS control wiring and terminations.
d. Verify voltage of battery modules.
e. Verify neutral and ground conductors are properly landed.
f. Inspect external maintenance bypass switch for proper terminations and phasing.
4. Site Testing:
a. Ensure proper system start-up.
b. Verify proper firmware control functions.
c. Verify proper firmware bypass operation.
d. Verify proper maintenance bypass switch operation.
e. Verify system set points.
f. Verify proper inverter operation and regulation circuits.
g. Simulate utility power failure.
h. Verify proper charger operation.
i. Document, sign, and date test results.
5. On-Site Operational Training: During the factory-assisted start-up, operational training for
site personnel shall include, but shall not be limited to, key pad operation, LED indicators,
start-up and shutdown procedures, maintenance bypass and AC disconnect operation, and
alarm information.
3.3 FIELD QUALITY CONTROL
A. General: See [Section 01 45 23 - INSPECTING AND TESTING SERVICES]
[Section 01410 - INSPECTING AND TESTING SERVICES].
B. Manufacturer Field Service:
1. Worldwide Service: The UPS manufacturer shall have a worldwide service organization
available, consisting of factory-trained field service personnel to perform start-up,
preventative maintenance, and service of the UPS system and power equipment. The
service organization shall offer 24 hours a day, 7 days a week, 365 days a year service
support.
2. Replacement Parts: Parts shall be available through the worldwide service organization
24 hours a day, 7 days a week, 365 days a year. The worldwide service organization shall
be capable of shipping parts within four working hours or on the next available flight, so that
the parts may be delivered to the Owner within 24 hours.
3.4 DEMONSTRATION
A. General: Provide the services of a factory-authorized service representative of the manufacturer to