Post-Installation System Checklist Procedures
8 Symmetra
®
LX Start Up Guide
Post-Installation System Checklist Procedures
Complete the tasks in the system checklist to ensure that the UPS is properly installed.
UPS System Checklist
1 . Ensure that the “Post-Installation Procedures for the UPS,” beginning on page 2 are successfully
completed.
2 . If your configuration includes Extended Run Cabinet(s), ensure that the “Post-Installation
Procedures for the Extended Run Cabinet (Optional),” beginning on page 5 are successfully
completed.
3 . If your equipment is installed in a rack, ensure that all components are securely mounted.
4 . Ensure that all modules (power, battery, and intelligence) are fully installed.
5 . Check that the PowerView is connected to the primary Intelligence Module (IM).
6 . Turn ON the AC utility power to the UPS.
7 . Turn ON the Input Circuit Breaker
D
and System Enable
E
switches.
8 . The system will make some clicking sounds as it powers up, and may display fault messages on
the PowerView display. Disregard the messages at this time. Press the 'Esc' button until the
Monitoring screen is displayed.
9 . Turn the Maintenance Bypass
F
switch ON.
10.Disregard any LED indicators or messages on the PowerView. Press the 'Esc' button until the
monitoring screen is displayed.
Note
Refer to the Symmetra
®
LX Physical Installation Manual and the Symmetra
®
LX
Electrical Installation Manual for detailed information concerning the steps
outlined in the checklist procedures.
.