4.0 Installation
4.10 Module interconnections (continued)
Follow the instructions below to install the battery communications cables.
4.10.5 Mate the battery cable plugs in the fashion illustrated below.
4.10.6 Each cable must connect between a Battery Pack OUTPUT and either the
UPSs BATT COMM input, or another Battery Pack INPUT.
TO: UPS BATT COM, or
TO: Battery Pack INPUT
FROM: Battery Pack OUTPUT
(multiple Battery Pack systems)
Typical installation showing mated battery communications cables.