NetworkAir RM Air Distribution Unit 5
Overview
Tools required You will need the following to install the Air Distribution Unit:
Pencil
Saw or other tool for cutting a hole in the raised floor
tile(s) (raised floor application only)
Caged nut tool (provided)
7-mm spanner or nut driver
Phillips screwdriver
Overview of the
installation
procedure
The Air Distribution Unit can be installed in both raised-floor
and non–raised-floor applications. The unit is installed in the
bottom 2U of the NetShelter enclosure or other 19" EIA 310-D
enclosure with an open or removable floor. The raised floor
application will require an opening in the raised floor, directly
under the enclosure. With the enclosure in place, install several
parts of the Air Distribution Unit so that you can mark the
location and size for this opening. Then move the enclosure
and remove the floor tile(s) to cut the opening. After
reinstalling the tiles and the enclosure, complete the
installation. See the following paragraphs in this section for the
installation procedure.
Equipment
placement
To avoid interference with air flow, use the uppermost part of
the enclosure for any equipment that extends forward over the
air outlet of the Air Distribution Unit.