However, retaining walls may not be necessary with the low noise levels of fuel
cell systems. In fact, the EPC recommends fuel cells for power generation in
order to obtain these points [72].
Sustainable Sites Credit 5.5: Site Development, Air Quality and Emissions Impact
This credit is also new to the NC Version 2.2 rating system. In order to reduce
emissions and the negative impact on air quality, the EPC recommends installing
a fuel cell power system. In order to receive a point for this credit, calculations
for NO
x
and CO emissions must be submitted and be a minimum of 10% better
than the local code requirement. It must also be shown that the emissions meet
or exceed the EPA Tier 2 standards [72].
Energy & Atmosphere Credit 2: Optimize Energy Performance
This credit is a modification of the Energy & Atmosphere Credit 1: Optimize
Energy Performance in the LEED NC Version 2.2 rating system. The range of
points available for this credit is 10 to 34 points. These points correlate with an
energy performance improvement over ASHRAE/IESNA Standard 90.1-2007 of
5% to 17.5% and 2% to 14% for new and existing buildings, respectively. The
draft states that since data centers can be 10 to 100 times as energy intensive as
an office building, it can be very difficult and expensive to reach the percentage
thresholds for commercial buildings as required by the NC Version 2.2 rating
system. Therefore, the EPC has decreased the thresholds and increased the
amount of points attainable [72].
Energy & Atmosphere Credit 4: On-Site Generation
This is another new credit added by the EPC Guide for Data Centers. This credit
encourages the use of on-site power generation in order to “reduce the
environmental and economic impacts associated with fossil fuel energy use and
transmission losses from utility power plants” [72]. The EPC also recommends
applying fuel cells for this credit. Up to three points are available for this credit,
depending on a percentage of improvement over ASHRAE/IESNA Standard
90.1-2007 in annual source energy [72].