InRow RC Operation and Maintenance8
Commissioning
Warning: Procedures in this chapter should only be performed by qualified,
APC-trained personnel.
Warning: Equipment must be properly de-energized and locked-out before performing
any service.
After installation, complete the following checklists to verify that all components are working properly
and that the equipment is ready to begin operation.
Checklists
Initial inspection
Warning: Equipment must be properly de-energized and locked-out before performing
any service on this equipment.
Never operate the equipment unless all covers, guards, doors, and panels are in place
and locked.
All electrical wiring must comply with national and local codes.
The equipment is grounded through its power cord. Ensure the equipment is connected
to a grounded outlet.
Electrical inspection
Ensure that the:
Installation procedure is complete according to the installation manual.
Equipment shows no signs of damage.
Clearance around the equipment is in accordance with ASHRAE, local, and national codes as well as the
installation manual.
Equipment is either secured to a rack or fastened to the floor.
Room humidity is below 60% relative humidity and all other room cooling equipment is functioning
before starting this equipment.
Ensure that the:
Incoming voltages match the phase and voltage rating on the nameplate.
Equipment is properly grounded to an earth ground.
Internal electrical components and terminal blocks do not have any loose connections.
Electrical connections are tight, including controllers and auxiliary devices.
Feeds A and B are properly connected.