InRow RC Operation and Maintenance36
Mechanical
Check the fans. All components should be moving freely with no signs of binding or damages.
Verify that the condensate line is flowing freely.
Verify the chilled water supply temperature for cooling unit.
Chilled water supply temperature________________________
Electrical
Before checking the electrical connections shut off and lock out the power to the cooling unit.
Inspect the electrical panel for tight connections and overheated connections from loose contact terminals.
Confirm the incoming main power matches the requirements listed on the cooling unit nameplate. The
measurement should be within 10% of the nameplate listing.
Quarterly Preventive Maintenance
Perform all the Monthly Preventive Maintenance items and the items below.
Prepared By: _________________________________
Model Number: ______________________________
Serial Number: _______________________________
Date: _________________
Mechanical
Before you perform mechanical checks, you must shut off and lock out the power to the cooling unit.
Verify that the fan hardware is tight.
Clean or replace filters.
Clean condensate pans.
Clean condensate drain line.
Remove any debris from condensate floats.
Clean dust from door perforations.
Clean dust from fan bezels.
Functional tests
Verify the cooling operation mode.
Verify the operation of the chilled water actuator.
Page view 43