28 Smart-UPS
®
VT 10-40kVA, 400V, Site Preparation and Installation Manual – 990-1986
Site Preparation Checklist
System components. Have you –
Site Preparation. Have you –
Arrival Preparation. Have you –
5
determined minimum battery run time requirement based on load (kW and kVA) and selected the
proper number of XR Enclosures (APC SUVTBXR2B6S and APC SUVTBXR6B6S) and Battery
Modules (SYBT4).
5
considered Service Program or Extended Warranty plan?
5
verified that input voltage and current are available?
5
considered correct operating space, floor strength (see Installation Space Requirements), cooling,
and environment (see Operating Environment).
5
reviewed all electrical work to determine wiring requirements?
5
verified that space and handling equipment are available to receive the UPS/XR Enclosure?
(Including unloading the UPS/XR Enclosure from the delivery truck ).
5
scheduled an electrician to install the UPS/XR Enclosure?