Electrical Installation – Wiring
34 Smart-UPS® VT 10-40kVA 400V Site Preparation and Installation Manual 990-2283
Input/Output Wiring – Dual Mains
The UPS is designed for single mains installation as default. Carry out the “Total-Power-Off
Procedure” on page 26, and follow the below instructions to install the UPS in a dual-mains
installation.
Loosen the 14 (13 in 352mm enclosure) M4 with torque screwdriver from the cover for the
cable termination area and remove.
Cut a cross in the blanking plugs.
Route the cables through the blanking plugs and into the cable land area.
Remove the 2 torque screws from brackets A, B, and C and remove all 3 brackets.
Note
The illustrations show 523mm Enclosures, but the installation procedures are identical
for 352mm Enclosures.
A
B
C