17MGE™ Galaxy™ 3500 10-40 kVA 380/400/415 V, 10-30 kVA 208/220 V Battery Installation
Install power cables between two XR Battery Enclosures.
1. Feed the cable up
through the conduit
box on XR1 or
through the
transparent cable
route bracket (not
shown) to the cable
connection area.
2. Connect the (-) cable
to busbar no. 5 (-), the
N cable to busbar no.
3 (N), and the (+)
cable to busbar no. 2
(+) in XR1.
3. Secure the cable to
the perforated bracket
with cable ties.
4. Equip the cable with
conduits (if
applicable).
5. Feed the cable up into
the conduit box
(optional for 400 V
versions) on XR2.
6. Connect the (-) cable
to busbar no. 6 (-), the
N cable to busbar no.
4 (N), and the (+)
cable to busbar no. 1
(+) in XR2.
7. Secure the cable to
the perforated bracket
with cable ties.
8. Attach the top part of
the conduit box (if
applicable).
Note: If you use floor anchoring, carry out the floor anchoring procedures now.
BAT
BAT
BAT
BAT
XR1 Battery Enclosure rear view
XR2 Battery Enclosure rear view
To XR3
From UPS