Electrical Installation – Input/Output Wiring – Single Mains (default)
AIS® 3000 10-30kVA, 208V, Site Preparation and Installation Manual – 990-1957 33
Punch 2 holes in the marked areas of the Conduit Box bottom to fit the size of the conduit pipes.
Attach the Conduit Box bottom to the Enclosure, using (4) M4x13 screws.
Install conduit pipes in the Conduit Box.
Run cables through the conduit pipes and the bottom of the Conduit Box, guides cables up into
the input/output area.
Install the top part of the Conduit Box to the Enclosure.
Attach input cable lugs on L1, L2 and L3 input busbars (left side in the UPS), using the
provided M6 hex screws. Attach output cable lugs on L1, L2 and L3 output busbars, using the
provided M6 hex screws. Attach N x 2 where shown, using the provided hex screws.
Attach Ground x 2 where shown, using the provided hex screws.
Reinstall the Plate, following reversed deinstallation procedures.
N
N
L
1
L
3
L
2
L
3
Batt+
Batt—
N
L
2
L
1
Ground
cables
Input
cables
Output
cables
Neutral
Plate covering cable
termination area