Installation and Start-Up60kW InfraStruXureTM SystemLarge Data Centers208/480/600 V Input
2 InfraStruXure System—Installation and Start-UpWarningsReceiving/movingDo not tilt the PDU greater than 45° from its vertical axis. Never lay the PDU
Safety: WarningsInfraStruXure System—Installation and Start-Up 3Total Power Off1. Set the PDU Main Input to OFF. 2. Set the upstream power source feed
InfraStruXure System—Installation and Start-Up 5Site PlanningDimensionsInfraStruXure PDUNetShelter VX EnclosurePDU Shielding Trough7.2in(183mm)23in(58
6 InfraStruXure System—Installation and Start-UpSpace ConsiderationsStudy the figure below to determine your space requirements for installing the Inf
InfraStruXure System—Installation and Start-Up 7Weight ConsiderationsEnsure that the floor and sub-floor can support the total weight of the configura
8 InfraStruXure System—Installation and Start-UpHeat OutputConsider the heat dissipation ratings of equipment to determine cooling requirements. Addit
InfraStruXure System—Installation and Start-Up 9Electrical Requirements and SpecificationsProcedures requiring a licensed electricianElectrical requir
10 InfraStruXure System—Installation and Start-UpEmergency Power Off (EPO)OverviewTo provide a mechanism for emergency power off, attach a remote swit
InfraStruXure System—Installation and Start-Up 11Basic Installation ProcedureThis section provides the basic steps that you need to perform when insta
208/480/600V
Site Planning: Basic Installation Procedure12 InfraStruXure System—Installation and Start-Up8. Install Shielding Troughs, Shielding Partitions, and Ca
InfraStruXure System—Installation and Start-Up 13Installation ProceduresLevel the PDU and NetShelter EnclosuresLeveling feet are attached under the en
14 InfraStruXure System—Installation and Start-UpConnect the Power Source to the PDUAccess the PDU Main Input switchOpen the back doors of the PDU, un
Installation Procedures: Connect the Power Source to the PDUInfraStruXure System—Installation and Start-Up 15– In the top of the PDU for overhead wiri
Installation Procedures: Connect the Power Source to the PDU16 InfraStruXure System—Installation and Start-UpInstall a circuit breakerDetermine the am
Installation Procedures: Connect the Power Source to the PDUInfraStruXure System—Installation and Start-Up 17Connect input conductorsAt the Main Input
18 InfraStruXure System—Installation and Start-UpConnect an Emergency Power Off SwitchOverviewConnecting the switch. The Emergency Power Off (EPO) swi
Installation Procedures: Connect an Emergency Power Off SwitchInfraStruXure System—Installation and Start-Up 19Connect an EPO switch to the user conne
Installation Procedures: Connect an Emergency Power Off Switch20 InfraStruXure System—Installation and Start-Up3. Test the EPO switch to ensure that i
Installation Procedures: Connect an Emergency Power Off SwitchInfraStruXure System—Installation and Start-Up 21Safety warningsHazardous voltage from t
InfraStruXure System—Installation and Start-Up iAbout this ManualThis manual is intended for APC Field Service Engineers or APC-trained installers of
22 InfraStruXure System—Installation and Start-UpConnect User Input Contacts and Relay Outputs to the User Connection PlateOverviewMake contact closur
Installation Procedures: Connect User Input Contacts and Relay Outputs InfraStruXure System—Installation and Start-Up 23How to connect contacts to the
24 InfraStruXure System—Installation and Start-UpInstall Shielding Troughs, Shielding Partitions, and Cable LaddersShielding Troughs and Shielding Par
Installation Procedures: Install Shielding Troughs, Shielding Partitions, InfraStruXure System—Installation and Start-Up 25Shielding Partitions. There
26 InfraStruXure System—Installation and Start-UpInstall InfraStruXure Rack-Mount DevicesInstall the Rack Automatic Transfer Switches (ATS)Install a R
InfraStruXure System—Installation and Start-Up 27Route and Attach Overhead WiringRoute and attach power cables to equipment racksIf you ordered overhe
Installation Procedures: Route and Attach Overhead Wiring28 InfraStruXure System—Installation and Start-Up– For dual-feed devices within a redundant s
Installation Procedures: Route and Attach Overhead WiringInfraStruXure System—Installation and Start-Up 295. From each NetShelter VX Enclosure, run th
30 InfraStruXure System—Installation and Start-UpWiring Under the FloorIf you are routing power cables to the enclosures under a raised floor, you mus
Installation Procedures: Wiring Under the FloorInfraStruXure System—Installation and Start-Up 315. At the circuit breaker panel, cut the wires to the
32 InfraStruXure System—Installation and Start-UpRoute Data Cables to the InfraStruXure Manager Hub (or Switch)1. Connect a Cat-5 network cable (provi
InfraStruXure System—Installation and Start-Up 33Start-Up ProcedureSafety warningsThis section provides instructions on how to perform a system start-
Start-Up Procedure: InfraStruXure System34 InfraStruXure System—Installation and Start-UpApply power to the system1. Set the upstream input circuit br
Start-Up Procedure: InfraStruXure SystemInfraStruXure System—Installation and Start-Up 356. If applicable, set the Main Output circuit breaker on the
36 InfraStruXure System—Installation and Start-UpConfigure the InfraStruXure ManagerOnce all equipment is installed, the network cables are connected
InfraStruXure System—Installation and Start-Up 37Appendix A: OperationHow to Apply Power to the SystemThis procedure instructs on how to apply power t
Appendix A: Operation38 InfraStruXure System—Installation and Start-Upb. For PDUs with and without a transformer: Close (turn On) the PDU distribution
InfraStruXure System—Installation and Start-Up 39How to Ensure Total Power Off 1. Open (turn OFF) the main circuit breaker on the power source feeding
InfraStruXure System—Installation and Start-Up 41Appendix B: Changes in This ManualOverviewThe following list references the specific changes made to
ContentsInfraStruXure System—Installation and Start-Up iiiSafety ...1Overview . .
IndexInfraStruXure System—Installation and Start-Up 43Aautomatic transfer switch, installing, 25Ccable ladders, installing, 24circuit breaker size, de
44 InfraStruXure System—Installation and Start-UpTtools required, 16torque specifications, 16total power offensuring, 33, 39warnings, 3Uupdatesin this
iv InfraStruXure System—Installation and Start-UpRoute the input conductors to the Main Input circuit breaker (or switch) . . . . . . . . . . . . . .
*990-1638B*APC Worldwide Customer SupportCustomer support for this or any other APC product is available at no charge in any of the following ways:• V
Appendix A: Operation ...37How to Apply Power to the System . . . . . . . . . . . . . . . . . . . . . 37How to
InfraStruXure System—Installation and Start-Up 1SafetyOverviewSave these instructionsThis manual contains important instructions that must be followed