Installation Procedures: Connect the Power Source to the PDU
16 InfraStruXure System—Installation and Start-Up
Install a circuit breaker
Determine the amperage of circuit breaker that you need to install:
Route the input conductors to the Main Input circuit breaker (or switch)
1. Route the input conductors to the Main Input circuit breaker (or switch) of the PDU, as follows:
For overhead wiring, run the input conductors directly to the Main Input circuit breaker (or
switch).
For wiring under a raised floor, run the input conductors through
the wireway (
) within the PDU to the Main Input circuit
breaker (or switch).
Torque specs and tools required
Before connecting to the terminals, verify the torque specs below by checking the specifications on
the Main Input circuit breaker (or switch).
Warning
Make sure the cables used for power input are sufficiently protected by a circuit
breaker.
Input Voltage Circuit Breaker Amperage
208V 225A
480V 90A
600V 75A
Termina l Torq ue Tools
L1, L2, L3, N 150 in-lb 6-mm Allen wrench
G, GEC 4 – 6 AWG: 45 in-lb
8 AWG: 40 in-lb
Slotted screwdriver