3. Verify proper firmware bypass operation.
4. Verify proper bypass switch operation (where applicable).
5. Verify proper inverter operation and regulation circuits.
6. Simulate utility power failure.
7. Verify proper charger operation.
8. Document, sign, and date all test results.
E. On-Site Operational Training: During the factory assisted start-up, operational training for site
personnel includes key pad operation, LED indicators, start-up and shutdown procedures,
maintenance bypass and AC disconnect operation, and alarm information.
3.2 FIELD QUALITY CONTROL
A. Manufacturer Field Service:
1. Worldwide Service: The UPS manufacturer has a worldwide service organization
available, consisting of factory-trained field service personnel to perform startup,
preventive maintenance, and service of the UPS system and power equipment. The
service organization offers service support 24 hours a day, 7 days a week, 365 days a
year.
2. Replacement Parts: Parts are available through the worldwide service organization
24 hours a day, 7 days a week, 365 days a year. The worldwide service organization is
capable of shipping parts within four working hours or on the next available flight, so that
the parts may be delivered to the customer site within 24 hours.
3.6 MAINTENANCE
A. A complete offering of preventative and full service maintenance contracts for the UPS system
and the battery system are available from APC by Schneider Electric. Contract work is
performed by Schneider Electric factory-trained service personnel.
END OF GUIDE SPECIFICATION