Assembling 2000 kVA SSCs >
34020846EN/AE - Page 61
2. Appendices
2. Appendices
2.1 Assembling 2000 kVA SSCs
2.2 IP 32 option
Refer to the "IP 32" manual no. 3460028300 for more details on this option
1 - Place the cabinets in their definitive
position
2 - Adjust the front feet to ensure the
cabinets are vertical and the doors
aligned.
3 - Remove the two inter-cabinet
uprights (1) located behind the right
hand side cabinet.
Fit the fishplates between the two
cabinets (fourteen fishplates supplied in
total):
4 - Align the fishplates horizontally
5 - Fit the two upper-part fishplates L1,
L2, L3 (2) (six fishplates in total)
between the 2 cabinets.
6 - Fit the two neutral fishplates (3)
between the two cabinets.
7 - Fit the two lower-part fishplates L1,
L2, L3 (4) (six fishplates in total)
between the 2 cabinets.
8 - Connect the two earthing braids (5)
between the front uprights of both
cabinets
9 - Connect the auxiliary wires between
the connectors (6) of both cabinets
10 - Fit the inter-cabinet uprights (1)
between the two cabinets
1
1
Right hand side cabinet
Rear view
12
11
15
13
14
6
X 2
X 3
X 1
Left hand side cabinet
Right hand side cabinet
Front view