APC Smart-UPS VT 400 Technical Information Page 21

  • Download
  • Add to my manuals
  • Print
  • Page
    / 46
  • Table of contents
  • TROUBLESHOOTING
  • BOOKMARKS
  • Rated. / 5. Based on customer reviews
Page view 20
Operation – Parallel System
990-2282C-001 Smart-UPS® VT 10-40 kVA 400V, 208V, 200V – Operation 15
From the external MBP: Check that all the output lamps (H2) at Q2 are lit.
From the external MBP: Turn all output switches (
Q2) to position “O” (OFF).
From the external MBP: Turn all input switches (
Q5) (if available) to position “O” (OFF).
From the external MBP: Turn all input switches (
Q1) to position “O” (OFF).
From the XR Enclosure(s) (if available): Set the DC disconnect switch(es) to position
OFF.
From the UPS: Disconnect the batteries by pulling them out to the red disconnect line shown on
each battery unit.
From the XR Enclosure(s) (if available): Disconnect the batteries by pulling them out to the red
disconnect line shown on each battery unit.
P
How to turn into normal operation from external maintenance bypass
Caution: Never attempt to turn the UPS into normal operation till you have verified that there
are no intenal UPS faults.
If the UPS units have been completely turned OFF, proceed with steps 2–16. If the UPS units have
not been completely turned
OFF, proceed with step 13–16.
From the UPS: Connect the batteries in each UPS by pushing them in.
From the XR Enclosure(s) (if available): Connect the batteries in each UPS by pushing them in.
From the XR Enclosure(s) (if available): Set the DC disconnect switch(es) to position ON.
From the external MBP: Turn all input switches (Q1) to position “| (ON).
From the external MBP: Check that all the input lamps (H5) at Q5 (if available) are lit.
From the external MBP: Turn all input switches (Q5) (if available) to position “|(ON).
From the external MBP: Check that all the output lamps (H2) at Q2 are lit.
From the external MBP: Turn all output switches (Q2) to position “|(ON). The lamp indicator of the
output isolation breaker
(Q4) is still lit.
From the UPS: Turn ON all UPS units from each display via Control–Turn Load ON–Yes, Turn
Load ON. The green online LEDs are lit on each UPS unit.
From the external MBP: Check that all the output lamps (H2) at Q2 are unlit and that all the input
lamps (
H5) at Q5 (if available) are unlit (continues on the next page).
From the UPS: Turn the UPS units into bypass from one UPS display via Control–UPS into
bypass–Yes, UPS into bypass. Check that the UPS units are in bypass. The green (
LOAD ON) and
the yellow (
BYPASS) LEDs are lit.
From the external MBP: Check that the lamp indicator of the output isolation breaker (
H4) is lit.
From the external MBP: Turn the output isolation breaker (
Q4) to position “|(ON). Now the lamps
H3 + H4 are lit.