9Smart-UPS® VT and MGE™ Galaxy™ 3500 10-30 kVA 208 V MBP Installation
Mounting the MBP
APC by Schneider Electric recommends mounting the MBP to 3/4 inches plywood backing (36 in
[914mm] high x 28 in [711mm] wide).
1. Attach the 3/4 inches plywood securely to the designated wall area. The wall should be strong
enough to support the 120lb [54.5kg] MBP. Leave at least 18in [457mm] of space between the
floor and the bottom of the plywood. Use appropriate hardware for the type of wall employed.
2. Measure and mark four (4) mounting-hole locations on the plywood backing. The locations will
be in the shape of a rectangle measuring 25.94in [659mm] across and 33.86in [860mm] down.
3. Drill starter holes in each of the four marked locations.
4. At least three people are needed to lift the MBP and position it against the plywood backing. Line
up the MBP’s four mounting holes with the four drilled starter holes.
5. Screw four (4) 1/4 x 1 inches hex-head lag bolts, along with four (4) 1/4 inches flat washers, into
the holes. Use a 1/2 inches socket with ratchet and tighten until rigid.
25.94 in [659]
33.86 in
Minimum 18 in [457] from floor!
[860]
1/4 x 1 in Lag Bolt (4)
1/4 in Flat Washer (4)