Smart-UPS® VT and MGE™ Galaxy™ 3500 10-30 kVA 208 V MBP Installation 10
Internal cable connections
For the convenience of the installer, ALL internal MBP cable connections were made prior to shipment.
Check to make certain the following internal cable connections were completed:
Power Terminal Block [L1, L2, L3, N, top-to-bottom] to Input Bus [L1, L2, L3, N, top-to-
bottom]
Output Bus [L1, L2, L3, top-to-bottom] to Input Fuse Block [L1, L2, L3, top-to-bottom]
Output Bus [N] to Neutral Bar [N]
Output Fuse Block [L1, L2, L3, top-to-bottom] to Panel Board [L1, L2, L3, left-to-right]
Neutral Bar [N] to Neutral Bar [N] (refer to “Internal components” on page 4)
Control Terminal Block to optional customer contacts [1, 2, 3, 4, 5, 6] and UPS connections for
Q3 [7, 8]. Note: The control wires from the UPS MUST
be connected to the Normally Closed
Auxiliary Contacts on Q3 [7, 8]. DO NOT
use terminals 5 and 6 for these connections! Refer to
“Schematic” on page 5 and to the appropriate wiring diagram in the UPS Installation Manual.
Power Terminal Block
to Input Bus [L1, L2, L3, N]
Output Bus
to Input Fuse
Output Bus
to Neutral Bar [N]
Output Fuse Block
to Panel Board
Block [L1, L2, L3]
[L1, L2, L3]