40 Implementing UPS Configurations with Microsoft Cluster Server
UPS Turn Off Delay: This period of time begins at power loss. After this
interval, the UPS turns off its output power (independent of any shutdown
completion). If line voltage returns during this period, turning off output
power is canceled (again independent of any shutdown operations in
progress). Possible delay values are 20, 180, 300, and 600 seconds. We
recommend that you set the value as estimated in the time line (Figure 19
on page 28).
UPS Wakeup Delay (Time): This is the time that the UPS must be
connected to a functioning power line before the attached systems can be
powered up. Possible delay values are 0, 60, 180, and 300 seconds.
Again, we recommend the maximum value of 300 seconds (to avoid
system boot in situations with short-time power return only). Additionally, a
percentage of full capacity for recharge may be specified as UPS Wakeup
Delay (Capacity).
Once you have set the parameters, click the OK button.
5. In the PowerChute PLUS main window (shown in Figure 32 on page 39),
select Configuration > Application Shutdown Parameters. Figure 34 will be
displayed.
Figure 34. Single UPS application Shutdown Parameters window
6. Disable the application shutdown (because this will be handled by the
command file UPS.CMD) and click the OK button.
7. In the PowerChute PLUS main window (shown in Figure 32 on page 39),
select Configuration > Event Actions. Figure 35 will be displayed.