990-2283 Smart-UPS® VT 10-40kVA 400V Site Preparation and Installation Manual 47
Wiring Verification Procedure
Use following procedure to verify that the UPS has been wired properly:
1. Make sure the DC breaker is in the OFF position.
2. Ensure all power wiring is torqued to 7Nm.
3. Switch the DC breaker in the ON position.
Note
If a problem occurs, call APC Customer Support. Refer to rear cover for contact
numbers.
4. Reinstall all rear cover and Front Panels to the UPS.
Note
If you have installed any optional equipment, refer to product-specific manuals.