EcoBreeze System Operation and Maintenance8
Inspection Checklists
Initial inspection
The initial inspection ensures that the equipment has been properly installed, the location of the
cooling unit has been properly prepared and the cooling unit is free of damage.
DANGER
HAZARD OF ELECTRIC SHOCK.
To avoid possible personal injury or death, the access door locking mechanism must be
re-engaged after access to a compartment for inspection or service requirements.
Failure to follow these instructions will result in death or serious injury.
WARNING
PRESSURIZED PIPING
The cooling unit operates under pressure. Take proper safety precautions when
connecting gauges or servicing piping.
Failure to follow these instructions can result in death, serious injury, or
equipment damage.
Ensure that:
The installation procedure is complete according to the requirements of the installation manual.
The Frame nameplate information, system configuration, and Module identification are recorded.
Exterior or interior structure, sheet metal, motors, pumps, coils, wiring, dampers, etc., do not
show evidence of damage.
The clearance around the equipment is in accordance with local and national codes and
regulations as well as this installation manual.
The supply water piping connections, external freeze protection, drain piping and connections,
routing comply with local and national codes and regulations.
Inspect supply and return air ducting at each Module, ensure ducts are open or closed properly;
check for gaps/air leakage on outdoor ducting.
Service platform installed and it allows for sufficient service clearance and in accordance with
local and national codes.
EcoBreeze Frame is properly placed and secured using TANDEMLOC VI-SO clamp connectors.
Return and supply ducts installed and properly attached to the cooling equipment.
Shipping materials have been removed.
Equipment is clear of any loose debris.
Water analysis completed and settings adjusted.
Page view 13