Site Preparation (UPS and XR) – Installation Space Requirements
12 AIS® 3000 10-30kVA, 208V, Site Preparation and Installation Manual – 990-1957
Clearance for 20.59in/523mm Enclosures in installations including an XR Enclosure
*) All physical installations must comply with NEC 110.26.
As floor anchoring is carried out prior to wiring (and to busbar connection between UPS
and XR Enclosures if applicable), allow for sufficient working space behind the unit for
electrical work to be carried out (including busbar connections between Enclosures if
applicable).
(E)
(D)
(A)
UPS
XR
(B)
Conduit Box (F)
(G)
(C)
(C)
Space requirements in mm
Minimum clearance above Enclosures (A) 20 508
Enclosure depth (B) 33.62 854
Enclosure width (C) 20.59 (x 2) 523 (x 2)
Minimum free rear space for ventilation* (D) 4 100
Minimum front clearance (E) 39.37 1000
Conduit Box, depth (F) 3.46 88
No side clearance required (include width of Stabilizing Bracket
for floor anchoring if applicable)*
00
Stabilizing Bracket width 3.34 85
Total installation depth, inclusive of Front Panel, Conduit Box
and minimum front and rear clearances (G)
80.39 2042