24 AIS® 3000 10-30kVA, 208V, Site Preparation and Installation Manual – 990-1957
Site Preparation Checklist
System components. Have you –
Site Preparation. Have you
Arrival Preparation. Have you –
5
determined minimum battery runtime requirement based on load (kW and kVA) and selected the
correct APC XR Enclosures (ISVTBXR2B6S, ISVTXR2B6S, ISVTBXR6B6S, ISVTXR6B6S)
and Battery Unit (SYBT1). Always install a whole Battery Module (4 Battery Units) at a time.
5
considered Service Program or Extended Warranty plan?
5
considered correct operating space, floor strength (see Installation Space Requirements), cooling,
and environment (see Operating Environment).
5
reviewed all electrical work to determine wiring requirements?
5
verified that space and handling equipment are available to receive the XR Enclosure? (Including
unloading the XR Enclosure from the delivery truck).
5
scheduled an authorized electrician to install the XR Enclosure?