Shipping, Receiving, and Unloading
Smart-UPS
®
VT Maintenance Bypass Panel w Power Distribution, 10-30kVA, 208V - 990-4199B 9
2. Record any damages observed and call the carrier immediately to allow their personnel to
conduct an equipment inspection, if necessary.
Do NOT contact APC firstnotify the carrier instead. Otherwise, APC may be unable to
assist in recovering the realized amount of the claim.
All damage claims should be as specific as possible. Information pertaining to the shipment
should appear on the shipping label and related paperwork.
BE SURE to request a copy of the carriers inspection report.
Unloading
1. Use a forklift or pallet-jack to transport the MBP to the installation site. Make certain the route
to the installation site can accommodate the size and weight of the unit (plus the lifting device).
2. At the installation site, remove a) the packaging material, b) the wooden ramp, and c) the plastic
sleeve (located inside the unit) containing the door keys and documentation. Also detach the
13/14mm wrench from the shipping pallet.
3. Use the 13/14mm wrench to remove the M8 bolt, and an M10 nut driver to remove the M6 bolt
from each of the four (4) angle brackets securing the MBP to its pallet.
Caution
Be aware that the MBP is shipped on its casters and may begin to roll once the bolts
have been removed. Take steps to prevent this from happening.
M8 Bolt
Angle Bracket
M6 Bolt