Site Preparation (UPS and XR) – Installation Space Requirements
14 AIS® 3000 10-30kVA, 208V, Site Preparation and Installation Manual – 990-1957
Clearance for 13.85in/352mm Enclosures in installations including XR Enclosures
*) All physical installations must comply with NEC 110.26.
(E)
(A)
(D)
UPS
XR
Conduit Box (F)
(G)
(C1)
(C2)
(B)
Space requirements in mm
Minimum clearance above Enclosures (A) 20 508
Enclosure depth (B) 33.62 854
Enclosure width (C1) 13.85 352
Enclosure width (C2) 20.59 523
Minimum free rear space for ventilation* (D) 4 100
Minimum front clearance (E) 39.37 1000
Conduit Box, depth (F) 3.46 88
No side clearance required (add width of Stabilizing Bracket for
floor anchoring if applicable)*
00
Stabilizing Bracket width 3.34 85
Total installation depth, inclusive of Front Panel, Conduit Box
and minimum front and rear clearances (G)
80.39 2042
For the stability of 13.85/352 mm stand-alone Enclosures, the transport brackets (re-use
of brackets used to secure the UPS to the shipping pallet) must always be mounted on
both sides of the UPS. Follow the Floor Anchoring procedures.