6739381EN/
Installation comprising modular UPSs with an external maintenance bypass
Fig. 3
The table opposite serves as an
example for an installation with up to
four modular UPSs with an external
maintenance bypass.
for installations with redundant units,
take into account only the units
required to supply the load power
(e.g. for an installation made up of 3
parallel-connected rectifier-inverter
cubicles, one being redundant, only 2
units are used to determine the
currents on the maintenance bypass
line and the load, and the cross-
sectional areas of cables);
this table has been drawn up for
rated phase-to-phase Mains 2 and load
voltages of 415V and full rated load
with a power factor of 0.8. For voltages
of 380 or 400V, multiply the indicated
currents by 1.09 and 1.04 respectively,
then modify the cable cross-sections
accordingly if necessary.
The cable cross-sections in this table
are for the parts illustrated in bold on
the following block diagrams
(installation example, figure 3);
important. In an installation with an
external maintenance bypass, the
power cables between each UPS and
the upstream protection devices
must be the same length. The same
holds for the power cables between
each UPS cubicle and the external
maintenance bypass.
Parameters for connection of the external maintenance bypass circuit and the
load in an installation comprising modular UPSs
rated inverter number of total UPS Mains 2 or load cable cross-section
output parallel-connected rated output line current (1) in mm
2
in kVA inverters in kVA in Amps Copper Aluminium
250 2 500 722 2 x 185 2 x 300
3 750 1082 3 x 300 4 x 240
4 1000 1444 4 x 240 4 x 400
300 2 600 866 2 x 240 4 x 185
3 900 1299 4 x 240 4 x 400
4 1200 1732 Please consult us*
400 2 800 1154 4 x 185 4 x 300
3 1200 1731 Please consult us*
4 1600 2308 Please consult us*
450 2 900 1299 4 X 240 4 x 400
3 1350 1948 Please consult us*
500 2 1000 1444 4 X 240 4 x 400
3 1500 2166 Please consult us*
(1) cable cross-sections are given for copper
conductors of the U1000 R02V type. They are
calculated according to permissible temperature
rise and allow for line voltage drops over a
maximum length of 100 m. For greater lengths,
the cross-sections should be chosen to limit
voltage drops to 3%.
maintenance Bypass cubicle
mains 1
inverter 1
inverter 2
inverter 3
load
mains 2
mains 1
mains 2
mains 1
mains 2
Characteristics (cont.)
NF C 15-100 authorizes a maximum of 4