InfraStruXure System—Installation and Start-Up 9
Electrical Requirements and Specifications
Procedures requiring a licensed electrician
Electrical requirements
Electrical
Hazar
Procedures requiring a licensed electrician include:
• Connection of utility conductors
• Installation of a 225-, 90-, or 75-amp circuit breaker
• Connection to the Main Input switch
• Wiring under the floor
See als
To connect utility conductors, see Certified Electrician’s Instructions included with
your PDU documentation.
208V Input 480V Input 600V Input
Service distribution breaker
†‡
225A 90A 75A
Conductors to main input switch
†
Transformer: 3W + G + GEC
No Transformer: 4W + G
3W + G + GEC 3W + G + GEC
Recommended wire sizing
‡
L1, L2, L3, N 4/0AWG 3 AWG 4 AWG
G 6 AWG 8 AWG 8 AWG
GEC 4 AWG 8 AWG 8 AWG
† Provided by customer.
‡ The specifications are recommendations. Consult the NEC and local codes for requirements specific to your installation.