Installationand Start-up150 kW InfraStruXure®Power Distribution Unit480 V / 600 V
2 150 kW InfraStruXure Power Distribution UnitWarningsReceiving/movingDo not tilt the PDU more than 45° from its vertical axis. Never lay the PDU on i
Safety: Warnings150 kW InfraStruXure Power Distribution Unit 3Total power off procedure1. Open (turn OFF) the main input breaker on the PDU.2. Open (t
Safety: Warnings4 150 kW InfraStruXure Power Distribution UnitEMIThis equipment has been tested and found to comply with the limits for Class A digita
150 kW InfraStruXure Power Distribution Unit 5Site PlanningDimensionsInfraStruXure PDUNetShelter VX enclosure81 in (2060 mm)7.2 in(183 mm)Without PDU
6 150 kW InfraStruXure Power Distribution UnitSpace ConsiderationsStudy the figure below to determine your space requirements for installing the Infra
150 kW InfraStruXure Power Distribution Unit 7Weight ConsiderationsEnsure that the floor and sub-floor can support the total weight of the configurati
8 150 kW InfraStruXure Power Distribution UnitHeat Output Consider the heat dissipation ratings of equipment to determine cooling requirements. Additi
150 kW InfraStruXure Power Distribution Unit 9Electrical Requirements and SpecificationsElectrical requirements† Provided by customer. Copper conducto
10 150 kW InfraStruXure Power Distribution UnitEmergency Power Off (EPO)OverviewTo provide a mechanism for applying emergency power off, attach a remo
150 kW InfraStruXure Power Distribution Unit 11Basic Installation ProcedureThis section provides basic instructions for installing InfraStruXure power
This manual is available in English on the enclosed CD.Uživatelská pøíruèka v èeštinì je k dispozici na pøiloženém CD.Dieses Handbuch ist in Deutsch a
Site Planning: Basic Installation Procedure12 150 kW InfraStruXure Power Distribution Unit7. Connect an EPO switch to the PDU monitoring unit.8. Insta
150 kW InfraStruXure Power Distribution Unit 13Installation ProceduresLevel the PDU and NetShelter EnclosuresLeveling feet are provided under each bot
14 150 kW InfraStruXure Power Distribution UnitConnect the Power Source to the PDUAccess the PDU main input breakerOpen the back doors of the PDU by f
Installation Procedures: Connect the Power Source to the PDU150 kW InfraStruXure Power Distribution Unit 15– For overhead wiring: Remove the gland pla
Installation Procedures: Connect the Power Source to the PDU16 150 kW InfraStruXure Power Distribution UnitRoute the input conductors to the main inpu
150 kW InfraStruXure Power Distribution Unit 17Connect an Emergency Power Off SwitchOverviewConnecting the switch. The Emergency Power Off (EPO) switc
Installation Procedures: Connect an Emergency Power Off Switch18 150 kW InfraStruXure Power Distribution UnitConnect an EPO switch to the user connect
Installation Procedures: Connect an Emergency Power Off Switch150 kW InfraStruXure Power Distribution Unit 193. Test the EPO switch to ensure it is wi
Installation Procedures: Connect an Emergency Power Off Switch20 150 kW InfraStruXure Power Distribution UnitSafety warningsHazardous voltage from the
150 kW InfraStruXure Power Distribution Unit 21Connect User Input Contacts and Relay Outputs to the User Connection PlateOverviewMake contact closure
150 kW InfraStruXure Power Distribution Unit iAbout This Manual This manual is intended for APC field service engineers or APC-trained installers of a
Installation Procedures: Connect User Input Contacts and Relay Outputs to the User Connection Plate22 150 kW InfraStruXure Power Distribution UnitTo c
150 kW InfraStruXure Power Distribution Unit 23Install Shielding Troughs, Shielding Partitions, and Cable LaddersShielding troughs and shielding parti
Installation Procedures: Install Shielding Troughs, Shielding Partitions, and Cable Ladders24 150 kW InfraStruXure Power Distribution UnitShielding pa
150 kW InfraStruXure Power Distribution Unit 25Install InfraStruXure Rack-Mount DevicesInstall the Rack Automatic Transfer Switches (ATSs)Install a ra
26 150 kW InfraStruXure Power Distribution UnitRoute and Attach Overhead WiringRoute and attach power cables to equipment racksIf you ordered overhead
Installation Procedures: Route and Attach Overhead Wiring150 kW InfraStruXure Power Distribution Unit 27– For dual-feed devices within a redundant sys
Installation Procedures: Route and Attach Overhead Wiring28 150 kW InfraStruXure Power Distribution Unit5. From each NetShelter VX enclosure, run the
150 kW InfraStruXure Power Distribution Unit 29Wiring Under the FloorIf routing power cables to enclosures under a raised floor, you must provide the
Installation Procedures: Wiring Under the Floor30 150 kW InfraStruXure Power Distribution Unit5. At the distribution panel, cut the power cable to the
150 kW InfraStruXure Power Distribution Unit 31Route Data Cables to the InfraStruXure Manager Hub (or Switch)1. Connect a CAT-5 network cable (provide
150 kW InfraStruXure Power Distribution Unit 33Start-Up ProcedureSafety warningsThis section provides instructions on how to perform a system start-up
Start-Up Procedure34 150 kW InfraStruXure Power Distribution Unit3. Open (turn OFF) the main output breaker on the front of the PDU. Apply power to th
Start-Up Procedure150 kW InfraStruXure Power Distribution Unit 354. Close (turn ON) the main output breaker on the front of the PDU. 5. Close (turn ON
Start-Up Procedure36 150 kW InfraStruXure Power Distribution Unit6. Close (turn ON) all sub-feed breakers (if applicable).
150 kW InfraStruXure Power Distribution Unit 37Configure the InfraStruXure ManagerOnce all equipment is installed, network cables have been connected
150 kW InfraStruXure Power Distribution Unit 39Appendix A: OperationHow to Apply Power to the SystemThis procedure provides instruction for re-applyin
Appendix A: Operation40 150 kW InfraStruXure Power Distribution Unitb. Close (turn ON) the individual PDU distribution panel circuit breakers.c. Close
150 kW InfraStruXure Power Distribution Unit 41How to Ensure Total Power Off1. Open (turn OFF) the main circuit breaker for the power source feeding t
Contents150 kW InfraStruXure Power Distribution Unit iiiSafety ...1Overview . . . .
Index 150 kW InfraStruXure Power Distribution Unit 43AApplying powe
44 150 kW InfraStruXure Power Distribution UnitUUpdates, to this manual iWWarnings 2–4Wiring, under the flo
02/2008990-1983B*990-1983B*APC Worldwide Customer SupportCustomer support for this or any other APC product is available at no charge in any of the fo
iv 150 kW InfraStruXure Power Distribution UnitInstallation Procedures ... 13Level the PDU and NetShelter Enclo
150 kW InfraStruXure Power Distribution Unit vStart-Up Procedure ...33Safety warnings . . . . . . . .
150 kW InfraStruXure Power Distribution Unit 1Safety OverviewSave these instructionsThis manual contains important instructions that must be followed
Comments to this Manuals