Installation Procedures: Connect the Power Source to the PDU
16 150 kW InfraStruXure Power Distribution Unit
Route the input conductors to the main input breaker
Route the input conductors to the main input breaker on the PDU and connect the input wiring
according to the labels on the breaker and the following illustration. Refer to the table below (Torque
specs and tools required) for specific information about connecting to each terminal.
3-phase, 3-wire + ground + GEC to building steel
*
C
*
Other types of electrodes may be used if building steel is not available. Consult the NEC for
requirements.
Torque specs and tools required
Before connecting to the terminals, verify the torque specs below by checking the specifications on
the main input breaker.
Warning
Connect the conductors to the terminals according to the labels on the terminals.
Use copper conductors only.
GEC
G
L1
L2
L3
Terminal Torque Tools
L1, L2, L3 150 in-lb (17 Nm) 6-mm Allen wrench
G 4–6 AWG: 45 in-lb (5.0 Nm) Slotted screwdriver
GEC 2-4 AWG: 50 in-lb (5.6 Nm) Slotted screwdriver