150 kW InfraStruXure Power Distribution Unit 29
Wiring Under the Floor
If routing power cables to enclosures under a raised floor, you must provide the appropriate power
cables and equipment for installation, and a licensed electrician must route and connect the power
cables to the PDU circuit breakers. To wire each power cable to an enclosure:
1. Remove a knock-out filler in the floor of the PDU to create an opening for the cable.
2. Install Liquidite waterproof conduit under the floor from each enclosure to the PDU.
3. From the rack PDU or rack ATS in each enclosure, thread the appropriate power cable (for your
application) through the Liquidite conduit to the PDU.
4. At the PDU, route the cable through the opening you created in step 1 and then through the
wireway for connection to the upper circuit breaker distribution panel.
Electrical
Hazard
A licensed electrician must route and connect the power cables for under-floor
wiring.
Warning
Make sure all wire connections and circuit breaker connections are properly
torqued.