Site Planning: Basic Installation Procedure
12 InfraStruXure System—Installation and Start-Up
8. Install Shielding Troughs, Shielding Partitions, and Cable Ladders.
9. Install the Rack Automatic Transfer Switches (ATS), Rack Power Distribution Units, and other
InfraStruXure rack-mount devices.
10. Route and attach power cables to each Rack ATS and/or Rack PDU.
11. Route and attach communication cables to the InfraStruXure Manager hub (or switch).
12. Start the system.
Only qualified, APC-trained personnel may perform a system start-up.
13. Configure the InfraStruXure Manager.
See als
o
For instructions, see the manuals included with your Shielding Troughs,
Shielding Partitions, and Cable Ladders.
See als
o
For instructions, see the manuals included with your Rack ATS, Rack PDU, or
other InfraStruXure rack-mount device.
See page 25 for detailed instructions.
See page 30 for detailed instructions.
See page 31 for detailed instructions.
See als
o
For instructions, see the manual included with your InfraStruXure Manager.