Site Planning: Basic Installation Procedure
12 InfraStruXure System—Installation and Start-Up
8. Install Shielding Troughs, Shielding Partitions, and Cable Ladders.
9. Install the Rack Automatic Transfer Switches (ATS), Rack Power Distribution Units, and other
InfraStruXure rack-mount devices.
10. Route and attach power cables to each Rack ATS and/or Rack PDU.
11. Route and attach communication cables to the InfraStruXure Manager hub (or switch).
12. Start the system.
Only qualified, APC-trained personnel may perform a system start-up.
13. Configure the InfraStruXure Manager.
See als
For instructions, see the manuals included with your Shielding Troughs,
Shielding Partitions, and Cable Ladders.
See als
For instructions, see the manuals included with your Rack ATS, Rack PDU, or
other InfraStruXure rack-mount device.
See page 25 for detailed instructions.
See page 30 for detailed instructions.
See page 31 for detailed instructions.
See als
For instructions, see the manual included with your InfraStruXure Manager.