APC InfraStruxure Specifications Page 37

  • Download
  • Add to my manuals
  • Print
  • Page
    / 60
  • Table of contents
  • BOOKMARKS
  • Rated. / 5. Based on customer reviews
Page view 36
Installation Procedures: Route and Attach Overhead Wiring
InfraStruXure System—Installation and Start-Up 29
5. From each NetShelter VX Enclosure, run the power cable of the appropriate APC power
management device out the roof of the enclosure, through the notch in the rear side of the
Shielding Trough, to the connector of the appropriate power cable from the PDU. Plug the two
connectors together, and twist them clockwise to lock.
Note
The APC InfraStruXure Build-Out Tool allows you to attach three 20A, single-pole
breakers to one three-phase power cable if you are powering 120V (L-N) loads.
However, if you are powering 208V (L-L) loads, you must attach a three-phase
power cable to one three-pole, 20A breaker.
Page view 36
1 2 ... 32 33 34 35 36 37 38 39 40 41 42 ... 59 60

Comments to this Manuals

No comments