InfraStruXure InRow RC—Operation and Maintenance 41
Quarterly Preventive Maintenance
* Perform all the Monthly Preventive Maintenance items and the items below.
Prepared By: _________________________________
Model Number: ______________________________
Serial Number: _______________________________
Date: _________________
Mechanical
Before you perform mechanical checks, you must shut off and lock out the power to the cooling
unit.
Verify that the fan hardware is tight.
Clean/replace filters.
Clean condensate pans.
Clean condensate drain line.
Remove any debris from condensate floats.
Clean dust from door perforations.
Clean dust from fan bezels.
Functional tests
Verify the cooling operation mode.
Verify the operation of the chilled water actuator.