Page 32 - 6739380EN/JC
Maintenance (cont.)
Frequency converter or parallel
UPS with SSC
(figure 32)
During maintenance, the concerned
UPS or converter must be isolated from
Mains 1, its battery and the output
circuits of the other units.
inverter isolation
Proceed in the following order:
shut down the inverter (press the
"inverter off" button 7 for 3 seconds),
open isolating switches Q5N, QF1
and Q1 for that line.
The unit is powered down once the
capacitors have discharged (a few
minutes).
In redundant systems with at least one
redundant UPS, the other UPSs (or
converters) ensure continuity of power
to the load.
Fig. 32: frequency converter exemple
Modular UPS with external
maintenance bypass
(figure 31)
To service a number of modular UPSs
with an external maintenance bypass, it
is necessary to isolate them.
isolate the UPSs
Proceed in the following order:
shut down each inverter (press the
"inverter off" button 7 for three
seconds),
switch to the maintenance bypass
whereby the load will be directly
supplied by Mains 2 via Q3BP (close
Q3BP, then open Q5 in the
maintenance bypass cubicle),
open input switch Q4S on each UPS;
isolate each UPS from Mains 2 by
opening the upstream protection
devices,
open input switch Q1 on each UPS,
open output switch Q5N on each
UPS.
The UPSs are de-energised (except the
Mains 1 cables upstream of the Q1
switches on each UPS), but the load is
supplied with Mains 2 power via the
maintenance bypass. Complete
isolation of the installation requires
opening of the upstream protection
devices on both Mains 1 and Mains 2.
start-up
Once servicing is completed, proceed
in the following order:
close the input switches Q1 and Q4S
on each UPS,
close output switch Q5N on each
UPS,
close output switch Q5N in the
maintenance bypass cubicle,
open switch Q3BP in the
maintenance bypass cubicle,
close battery circuit breaker Q1 on
each UPS,
Fig. 31
start all the inverters (press the
"inverter on" button 6 ).
The UPSs all come on line at the same
time if they are sufficient in number to
supply the load.
Note. It is strongly advised to call on
our after-sales support department for
these operations.
mains 1
load
mains 1
mains 1
QF1
QF1
QF1
Q1
Q1
Q1
Q5N
Q5N
Q5N
Q1
Q5N
QF1
Q3BP
Q4S
Q1
Q5N
QF1
Q4S
Modular UPS 2
Modular UPS 1
Q5N
External maintenance bypass
load
battery
inverter
mains 1
rectifier-
charger
static switch
mains 2
battery
inverter
mains 1
rectifier-
charger
static switch
mains 2