InfraStruXure 20kW System: Installation, Operation, and Maintenance 21
Route and Attach Overhead Wiring
Route and attach power cables to equipment racks
If you ordered overhead wiring, connect the prewired power cables of the InfraStruXure 20kW
System as follows:
1. Install the Shielding Troughs, Shielding Partitions, and Cable Ladders so that you can route
power cables from the system to the NetShelter VX Enclosures.
2. Find the numbers that indicate the enclosure to which each power cable will supply power.
These numbers appear on the roof of the InfraStruXure 20kW System where the power cables
exit, and on the ends of each power cable.
3. Beginning with the power cables for the enclosures farthest from the system, run each power
cable within the Shielding Trough along the row and, if necessary, across one or more Cable
Ladders to the enclosure to which it will provide power.
4. Connect the appropriate power cable to APC power management equipment in the enclosure in
one of the four following ways:
For single-feed devices without redundancy: Attach a power cable directly to a Rack PDU
installed in a NetShelter VX Enclosure.
S
ee also
See the installation and grounding instructions in the manual included with your
Shielding Troughs, Shielding Partitions, and Cable Ladders.
Note
The enclosures are not numbered. Consult your APC InfraStruXure
Configuration Buildout Tool to determine the enclosure associated with each
power cable.
Note
Ensure that the L21-20 twist-lock connector at the end of each power cable
always lies on top of any longer power cables in the Shielding Trough.