Installation: Route and Attach Overhead Wiring
22 InfraStruXure 20kW System: Installation, Operation, and Maintenance
For dual-feed devices within a redundant system: Attach a power cable from each system into
two different Rack PDUs in the NetShelter VX Enclosure.
For single-feed devices within a redundant system with an Automatic Transfer Switch:
Connect a power cable to the Automatic Transfer Switch (A and B feeds), and connect the
Automatic Transfer Switch power cord to a Rack PDU in the NetShelter VX Enclosure.
For dual-feed devices in a redundant system with an Automatic Transfer Switch: Connect a
power cable from each system to the Automatic Transfer Switch’s A and B feeds, and another
power cable from one system to a Rack PDU, and the Automatic Transfer Switch’s power
cord to a second Rack PDU in the NetShelter VX Enclosure.
Note
Lay the cables neatly in the Shielding Trough to minimize cable build-up.